Jump to Content

Johnson Street, Pingelly - 056886-15WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Aug 2015 - May 2016
Australian Government Contribution:$73,556
Local Council/Shire:Shire of Pingelly
State:WA

Project Description

The road has a grade of 11% and storm water has caused the road shoulders to erode blocking the table drain and cause minor flooding to surrounding properties over a number of years

Install storm water drainage system including storm water pits and pipes then reshape the road prior to resealing with a 2 coat bitumen seal and install kerbing so storm water can be directing into the new storm water system

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2016