Jump to Content

Bambun Road, Rural Road - 057221-15WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2016 - May 2016
Australian Government Contribution:$155,612
Local Council/Shire:Shire of Gingin
State:WA

Project Description

Existing surface is badly corrugated and slippery increasing road maintenance costs and decreasing road safety. Road surface has reached the end of its life.

Resheet existing road surface with 100mm gravel for 7m wide for 3.50 kilometres long.

Total cost of proposed project is $178,901

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/10/2016