Shepparton Alternative Freight Route Enhancement Package

Funding Program:Investment Road and Rail Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Early 2017 - Mid 2018
Estimated Project Cost:$3,894,787
Australian Government Contribution:$2,250,000
Local Council/Shire:Greater Shepparton City Council
State:VIC

Project Description

The project will rehabilitate approximately 700 metres of pavement on Old Dookie Road between Mitchell Street and Doyles Road in Shepparton. The project will also remove the existing roundabout and signalise the intersection at New Dookie Road and Verney Road in Shepparton.

Benefits

The project is expected to improve safety and heavy vehicle productivity, reduce traffic congestion and improve local amenity.

Funding

The estimated cost of the project is $3,894,787. The Australian Government is contributing $2,250,000 and Greater Shepparton City Council $1,644,787.

Timetable

Construction commenced on 3 AprilĀ 2017 and is expected to be completed in mid 2018.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 20/10/2017