McKinlay Gilliat Road, Julia Creek - 058670-15QLD-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Oct 2015 - Aug 2016
Australian Government Contribution:$355,692
Local Council/Shire:Mckinlay Shire Council
State:QLD

Project Description

Increasing costs of road maintenance in both wet and dry weather. Road cannot be used after 20 mililitres of rain. The road needs to be realigned around a bend to make it safer to use. The road during the dry season requires extra maintanence as it becomes soft (like powder) which makes it unsafe.

Supply and place gravel pavement and two coat bitumen seal to improve access and reduce maintenance costs.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.