Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Yarralin internal road 1 - 058673-15NT-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jun 2016 - Oct 2016
Australian Government Contribution:$113,035
State:NT

Project Description

Existing road was built lower than the surrounding area which is creating dust during dry season and drain over the road during wet season.

Construction of Concrete Spoon Drain (110.5m x 1.2m x 150mm), Construction of 2 x Commercial Concrete Driveway (8m x 9m)(6m x 5.1m) Re-Instate Bitumen on existing trench that doesn’t have any Raise 1 x Telstra/Communications Pit to new finish level Install 1 x SEP drain in Northern Drainway

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2017