Jump to Content

Shands Road, Main Ridge - 058763-15VIC-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Nov 2015 - Jul 2017
Australian Government Contribution:$711,000
Local Council/Shire:Mornington Peninsula Shire Council
State:VIC

Project Description

The proposed upgrade of the existing bridge is in response to the bridge reaching its end of life cycle and requires replacement. The existing bridge structure is of a narrow two lane, timber deck with a steel substructure. The bridge is too narrow and does not allow for vehicles to safely pass each other. There is currently a reduced load limit and speed limit imposed on the bridge for safety reasons.

Replacement of the existing timber bridge structure including widening of existing road pavement at the approaches, bridge road pavement overlay, gaurdrails and precast concrete bridge. The recently completed Shands road upgraded was completed in 2014.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2017