Greendale Road, Bringelly - 058921-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2016 - Jun 2016
Australian Government Contribution:$140,748
Local Council/Shire:Liverpool City Council
State:NSW

Project Description

Pavement has reached the end of the serviceable life and is demonstrating signs of extensive cracking, rutting and failures.

Pavement reconstruction with 150mm asphalt concrete for along Greendale Road on either side of Dwyer Road intersection including regarding of shoulder, table drain and upgrade of intersection at Dywer Road

Total cost of proposed project is $715,289

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2016