Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Oct 2015 - Dec 2015
Australian Government Contribution:$308,000
Local Council/Shire:Richmond Shire Council
State:QLD

Project Description

The existing road is a gravel section between two bitumen surfaces. The gravel road gets heavily corrugated by roadtrains carting cattle. This section is prone to flooding and heavy vehicles get stuck on the road during wet weather.

It is proposed to form and shape up the existing road to allow for the correct crossfall. 300mm new gravel pavement will be added to the formation and bitumen sealed to 6.2m wide. Existing table drains and road shoulder will be regraded to allow controlled drainage of storm water.

Total cost of proposed project is $616,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/02/2017