Gabbin - Trayning Road (Rural Road) - 059115-15WA-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Aug 2015 - Nov 2015
Australian Government Contribution:$10,429
Local Council/Shire:Shire of Mt Marshall
State:WA

Project Description

The surface can be quite slippery when wet due to the surface being primarily clay

Construct a new 9.0 metre wide 150 millimetre thick compacted gravel pavement carriageway for a total of 300 metres. New gravel will be imported, spread, water bound and compacted to achieve the designated surface.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/03/2016