Department of Infrastructure and Regional Development print logo Building our Future print logo

Bertram Street - 059430-15QLD-RTR

Funding Program:Roads to Recovery Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Jun 2016 - Sep 2017
Australian Government Contribution:$900,000
Local Council/Shire:Rockhampton Regional Council
State:QLD

Project Description

Pavement and Kerb and Channel have failed

Replace Kerb and Channel,replace stormwater inlets,replace existing pavement,reseal with polymer modified bitumen seal and slurry seal.

Total cost of proposed project is $1,000,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2017