Project Description

Considerable pavement failure along with sub-surface drainage issues due to poor soil conditions. Extensive cracking and deformation has occurred along the asphalt wearing course, and will become a safety risk to motorists if not addressed in the near future.

Drainage installation along the length of road. Pavement reconstruction utilising a foam bitumen stabilisation to reduce construction times so that construction can be completed within school holidays. Works also include kerb and channel construction and vehicle/pram crossing construction.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/07/2016