Department of Infrastructure and Regional Development print logo Building our Future print logo

Cornelia Road, Toongabbie - 060526-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2016 - May 2016
Australian Government Contribution:$110,584
Local Council/Shire:Blacktown City Council
State:NSW

Project Description

The existing seal is oxidised and stripped. The pavement is displaying cracking in some areas. In general the shape of the road is acceptable.

The works involved milling and removal of the existing road seal and based layer. Laying 120mm of AC20 and 30mm of AC10 as final layer over the full width of the roadway.

Total cost of proposed project is $127,978

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.