Department of Infrastructure and Regional Development print logo Building our Future print logo

Dry Dock Road, South Tweed - 060845-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2015 - May 2016
Australian Government Contribution:$533,000
Local Council/Shire:Tweed Shire Council
State:NSW

Project Description

The existing sealed pavement of this sub-arterial road is in poor condition with numerous structural defects including cracking, rutting and localised pavement failures. The road provides poor ride quality for users and requires frequent patching with consequent high maintenance cost.

For the first two segments, strengthening of the pavement by excavating the upper layers of the existing pavement, then provision of a new deep-lift asphalt pavement. For the third segment, rehabilitation of the existing pavement by in-situ stabilisation with cement based binder, followed by spray sealing and asphalt surfacing.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/07/2016