Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2015 - Nov 2015
Australian Government Contribution:$205,000
Local Council/Shire:Ballina Shire Council
State:NSW

Project Description

Old pavement and seal has failed showing pavement rutting and shoving with significant patching, which requires high maintenance resources.

Reconstruction of pavement and seal for a length of approximately 380 metres with a width of 8 metres including removal and replacement of unsuitable subgrade material. Includes installation of approximately 150 metres of kerb and gutter and replacement drainage.

Total cost of proposed project is $255,759

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/03/2016