Jump to Content

Newland Street, Bondi Junction - 061300-15NSW-RTR

A A A

Funding Programme:Roads to Recovery Programme
Status:Completed
Transport Mode:Road
Expected Start/Finish:Nov 2015 - Dec 2015
Australian Government Contribution:$122,800
Local Council/Shire:Waverley Council
State:NSW

Project Description

Cracked, potholed and deterioration of road surface.

Mill existing wearing course and replace with new asphalt resheet.

Total cost of proposed project is $139,936

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2016