Haymet Street, Kirrawee - 061305-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Apr 2016 - Aug 2016
Australian Government Contribution:$355,194
Local Council/Shire:Sutherland Shire Council
State:NSW

Project Description

Significant pavement failure and is in need of renewal. Require drainage upgrade including provision of kerb and gutter.

Proposed works will replace the upper granular section of the base course with flexible pavement. Road pavement rehabilitation works for a length of 150m and width of 7.5m include mill and fill with 60mm thick asphalt base layer and 30mm wearing course. Works include provision of kerb & gutter and drainage upgrade.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/12/2017