Gabriel Street, CLOVERDALE - 061475-15WA-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:May 2016 - Jun 2016
Australian Government Contribution:$60,167
Local Council/Shire:City of Belmont

Project Description

Asphalt has cracking due to base course deformation. There has been a loss of stone in the wearing course as a result of the age of the asphalt and short sections of damaged kerb line need to be replaced along with drainage pit lifting to meet new finished road levels.

Length, width and area of the job: 185m x 11m = 2,035m2. Reconstruct the top half of the base course material including asphalt through a wet mix construction process. Replace damaged sections of kerb line, lift drainage pits to match final asphalt overlay. At grade median to be overlayed in red asphalt.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/08/2016