Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Hunter Road, MOONAN - 061722-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mar 2016 - Dec 2017
Australian Government Contribution:$843,393
Local Council/Shire:Upper Hunter Shire Council
State:NSW

Project Description

Narrow pavement (approximately 5 metres). Lack of suitable sight distance and pavement scoured by Hunter River.

Widening of road by excavation and blasting of rock. Construction of new pavement on new alignment. Stabilisation of river bank. Length of road to be upgraded 49.8km to 50.3km x 9m formation. Total seal area 4000m2

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2018