Quarrie Road, Biloela - 061820-15QLD-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:Mar 2016 - Mar 2016
Australian Government Contribution:$100,000
Local Council/Shire:Banana Shire Council

Project Description

Water ponds 400mm deep and prevents traffic from crossing the floodway

Remove existing floodway and install 7/2400 x 1200 Slab Link Box Culvert(Length of floodway 20m x 12m wide), reconstruct road - total length 100m)

Total cost of proposed project is $300,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/05/2016