Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Robinson Road, Borroloola, Northern Territory - 062153-15NT-RTR

Funding Program:Roads to Recovery Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Sep 2017 - Jun 2018
Australian Government Contribution:$291,110
State:NT

Project Description

The road currently has inadequate open storm water drains. The eroded gravel road reserve and open drains constantly flush gravel onto the sealed surface and have eroded the shoulders and seal edges.

Works will include: Concrete Footpath 2 metres wide, unreinforced 100 millimetre slab, 755 metres square; Spray Seal pavement, single seal, width 7 metres, 2,050 metres square; Raised Pavement (150 millimetres compacted gravel base), 6 metres square; Kerbing, 350 metres; Landscaping; Drainage pipe, 30 metres; 5 Side entry pits; 4 Concrete driveway crossover 6 metres wide, reinforced 150 millimetre slab; Contingency included.

Total cost of proposed project is $420,459

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2018