Cudgen Road, rural road - 062182-15NSW-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:May 2016 - Oct 2016
Australian Government Contribution:$106,797
Local Council/Shire:Tweed Shire Council

Project Description

The existing sealed road is in poor condition with numerous surface defects and pavement failures. The road is very rough and provides poor ride quality to road users. Repair of the frequent and repetitive pavement and surface failures causes high maintenance expenditure. Length 350m.

Rehabilitation of the road pavement by application of a gravel overlay and new sealed surface. Correct any crossfall deficiencies with the new gravel layer. The road alignment and width will remain similar to the existing road.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/03/2017