Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Massinger Street Byron Bay - 062680-15NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Apr 2016 - Jan 2017
Australian Government Contribution:$770,400
Local Council/Shire:Byron Shire Council
State:NSW

Project Description

Road condition consists of weak, thin and failing pavement with thin, failing bitumen seal. Surface condition consists of mostly pothole patches within the travel lanes and wheel paths. Intersection between Lawson St and Massinger Street limits traffic flow. Stormwater drainage at intersection and along Massinger Street requires upgrade.

Road reconstruction - 115m on Massinger St. Failed Pavement to be removed by profiler. New pavement (DGS40) to be placed in 215 mm layer. 2 courses of AC 20 to be placed totalling 135mm full depth AC thickness. 40mm AC14 wearing surface to be final surface. Massinger Street Road construction to enlarge pavement width to allow on street parking. Require drainage works - 200m of drainage works redirecting, collecting and increasing drainage capacity are to be constructed from Lighthouse and Massinger Street intersection to Massinger Street and Kipling intersection, then across Massinger Street to outlet. Works will also include culvert lengthening at outlet.

Total cost of proposed project is $792,400

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/04/2017