Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

River Torrens Linear Park Shared Use Path - 062723-15SA-RTR

Funding Program:Roads to Recovery Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Jul 2016 - May 2018
Australian Government Contribution:$1,153,053
Local Council/Shire:Corporation of the City of Norwood Payneham & St Peters

Project Description

The path is approximately 36 years old and is in poor condition due to age and tree root damage. Several defects and safety issues such as poor line of sight, excessive crossfall, steep grades, lack of compliant barrier fencing and narrow width will be corrected when the path is reconstructed.

Construction will commence in November 2016. The path will be constructed to a width of 4m (subject to site constraints) and will extend from Langman Grove, Felixstow to Battams Road, Royston Park, an approximate distance of 3.85km

Total cost of proposed project is $1,300,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/02/2018