Marion Street - 064066-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Feb 2017 - Mar 2017
Australian Government Contribution:$200,000
State:NSW

Project Description

Pavement condition is poor along traffic lane with rutted surface and crocodile cracking. Drainage condition is poor with ponding at few locations.

Milling out existing pavement surface and filled up 60-80mm AC20 and 40mm AC14, also reconstructing kerb and gutter, pram ramps and replacing lintel and grates

Total cost of proposed project is $215,448

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 17/05/2017