Wattle Street - 064069-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jan 2017 - Mar 2017
Australian Government Contribution:$300,163
State:NSW

Project Description

Wattle Street is a regional road with high density traffic flow. The existing pavement condition needs to be upgraded due to poor condition. Drainage issues with ponding at few sections

Reconstruction of kerb and gutter, pavement resurfacing by milling and filling with 60mm AC20, 40mm AC14 as per pavement design and associated traffic works.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/04/2017