Wrigley Street. (Gilgandra) – Stage Two (2) - 064811-16NSW-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:Feb 2017 - Apr 2017
Australian Government Contribution:$400,124
Local Council/Shire:Gilgandra Council

Project Description

Primary Town Street that was originally formed up with sandy black soil, with the existing seal being in excess of 30 years old. Longitudinal and lateral cracking has let moisture penetrate the base layer and the street is prone to excessive potholing and deformation. The kerb and gutter on both sides need replacing as well as the storm water inlets (lintels).

Remove existing kerb and gutter and storm water inlets; remove from site top 300mm of existing road base material. Reinstate kerb and gutter and storm water inlets (328m). Import certified sub base material, stabilize, form up and compact to a depth of 200mm then import Design Graded Base (DGB) material , form up and compact to a depth of 100mm, trim and shape to conform with new kerb and gutter, then bitumen seal using 10mm aggregate.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/09/2017