Rydal-Hampton Road (Rydal) - 064892-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2017 - Sep 2017
Australian Government Contribution:$272,543
Local Council/Shire:City of Lithgow Council
State:NSW

Project Description

Surface instability, aged seal and aged pavement have caused consistent pavement failure over this 1.5km section, just south of the Rydal township. Such failures include severe surface cracking and potholing.

The seal for this 1.5km section will be entirely removed and the pavement will be ripped and blended with new, suitable quality road base. The subsurface will then be compacted prior to the application of a robust 20/10 two-coat seal. Table drains will be reformed and stormwater drainage pipes will be reformed and cleared where applicable.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2017