Taylor Street - 065346-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Apr 2017 - Jun 2017
Australian Government Contribution:$195,000
State:NSW

Project Description

The pavement is in poor condition with the evident of fatigue cracking, ravelling and potholes. The road pavement requires the strengthening structurally and resurfacing. Pavement Area = 4,250 sq.m

Repair failed sections or weak spots of the pavement with 140mm AC20 (Approx. 300m2)and Mill and Fill 40mm AC Overlay full width

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/04/2017