Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2016 - Dec 2016 |
Australian Government Contribution: | $224,000 |
State: | NSW |
Project DescriptionSignificant damage to the asphalt pavement surface including surface cracking, localised pavement failure and presence of loose stones from asphalt delamination due to increased traffic in the area.
Remove existing pavement surface, repair failed sections and provide a new asphalt surface. |