Bass Highway - Westbury Road Intersection Upgrade

Funding Program:Investment Road and Rail Program
Status:In planning
Transport Mode:Road
Expected Start/Finish:Late 2018 - Early 2019
Estimated Project Cost:$2,359,000
Australian Government Contribution:$400,000
Local Council/Shire:Launceston City Council
State:TAS
Corridor:Hobart - Burnie

Project Description

The project will construct a roundabout at the junction of Westbury Road and the Bass Highway access road to replace the existing T-intersection. The project will also construct two additional access roads adjoining the roundabout.

Benefits

The project will reduce the frequency of crashes and deliver travel time savings at the junction of Westbury Road and the Bass Highway access Road.

Funding

The estimated cost of the project is $2,359,000. The Australian Government will contribute $400,000.

Timetable

Construction is expected to commence in September 2018 and be completed April 2019.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.