Barneson Boulevard and Tiger Brennan Drive Stage 3

Funding Program:Investment Road and Rail Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Mid 2018 - Mid 2020
Estimated Project Cost:$45,300,000
Australian Government Contribution:$29,500,000
State:NT
Corridor:Perth - Darwin

Project Description

The project involves the construction of a new link between Tiger Brennan Drive and Darwin CBD along with the completion of the duplication of Tiger Brennan Drive from Berrimah Road to the Darwin CBD. This enables commuter traffic to Darwin CBD through multiple entry/exits to be distriubted evenly. The upgrade will provide relief for the pressure on the CBD transport network that has resulted in declining levels of service and increasing delays.

Benefits

This project is expected to deliver the following benefits:

  • ease congestion and improve access to the Darwin CBD
  • consistent and reliable travel times
  • improved road infrastructure around Darwin CBD helps in attracting tourism and business and the flow on effects on business sustainability

Funding

The Australian Government is providing up to $29.5 million towards the project, with the Northern Territory Government providing $10.8 million and Darwin City Council providing $5 million.

Timetable

Construction commenced in May 2018, and is expected to be completed in mid-2020.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 14/06/2018