Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Tooloom Road (Rural Road) - 066689-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jul 2016 - Oct 2017
Australian Government Contribution:$456,784
Local Council/Shire:Tenterfield Shire Council
State:NSW

Project Description

The existing timber bridge has a 10 tonne load limit because it has deteriorated significantly. The length of the bridge is 28 metres and the width is 5.4 metres.

The entire bridge is being upgraded to comprise a concrete substructure with modular timber deck.

Total cost of proposed project is $612,119

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/11/2017