Project Description

The existing road pavement exhibits areas of severe roughness and loss of shape. In addition significant lengths of concrete kerbing is in a poor condition.

The project includes the following major aspects: • Reconstruction of 338 metres of existing road pavement • Reconstruction of 694 metres of existing kerb and channel • Reconstruction of existing vehicle crossings where required • Reconstruction of all damaged footpath • Construction of 637 metres of underground drainage works

Total cost of proposed project is $761,570

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.