Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Toral Drive - 067465-16QLD-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Dec 2016 - Mar 2017
Australian Government Contribution:$285,000
Local Council/Shire:Sunshine Coast Regional Council
State:QLD

Project Description

The proposed section has the following defects: extensive cracking including fatigue/crocodile cracking and longitudinal cracks, deep depressions along the length of the road in the wheel paths. The existing asphalt surface is old, oxidised and brittle. There are major surface failures and moderate pavement failures.

The proposed treatment consists of full depth asphalt pavement or in situ stabilisation of existing pavement and new asphalt surfacing including improvements to subsurface drainage.

Total cost of proposed project is $357,877

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 17/05/2017