Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Olinda Grove, Mount Nelson - 067684-16TAS-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Sep 2016 - Aug 2018
Australian Government Contribution:$562,859
Local Council/Shire:Hobart City Council
State:TAS

Project Description

Significant areas of the road pavement and wearing surface have failed, causing a poor/sub-standard and unsafe riding surface. The poor road condition also contributes to water ponding on the road thus increasing the risk of aqua planing.

In selected areas full depth pavement re-construction will be undertaken, together with total surface renewal over the entire section of road. The project will also include some drainage improvement works including new kerb and channel and minor pipe and gully pit installations. Incidental pedestrian improvement works are also part of the project.

Total cost of proposed project is $610,000

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2018