Mark Street - 067775-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Jan 2018 - Feb 2018
Australian Government Contribution:$190,000
State:NSW

Project Description

Significant damage to asphalt surface, surface deformation, localised road pavement failure and excessive cross-fall in some areas resulting road drainage problems.

Removal of existing asphalt surface, repair localized road pavement failures, road cross-fall correction and provision of a new asphalt surface

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2018