Penrice Road, Angaston - 068144-16SA-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Oct 2016 - Nov 2016
Australian Government Contribution:$144,188
Local Council/Shire:The Barossa Council
State:SA

Project Description

This section of road is a sealed road at the end of its useful life. The road surface has become porous and allows water to penetrate into the sealed surface.

AC10 hotmix - 40mm and AC14 hotmix - 60mm, 300 metres at an average width of 10 metres, as part of Council's reseal program to rehabilitate the surface and extend the seal life.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/03/2017