Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Bluff Road, Yowah (Rural) - 068748-16QLD-RTR

Funding Program:Roads to Recovery Program
Transport Mode:Road
Expected Start/Finish:May 2017 - May 2017
Australian Government Contribution:$25,000
Local Council/Shire:Paroo Shire Council

Project Description

Road becoming rutted and gravel unravelled.

Medium formation grade required to incorporate and blend extra material from the flanks to establish the correct profile.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.

Project details last updated: 10/07/2017