Chelmsford Avenue - 068803-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:May 2017 - Jun 2017
Australian Government Contribution:$125,000
State:NSW

Project Description

The road surface is old and affected by numerous cracks at trafficable lanes. Due to past treatments and current surface defects, the road surface is rough to ride on. It is also allows water to penetrate into road base causing pavement failures and surface deformations.

The proposed work includes reconstruction of trafficable lanes with asphalt and resurfacing of the road with asphalt. Length = 190 m; Width = 12 m; Area = 2280 m2.

Total cost of proposed project is $138,273

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/08/2017