Brisbane Avenue Barton - 091728-16ACT-RTR

Funding Program:Roads to Recovery Program
Status:In planning
Transport Mode:Road
Expected Start/Finish:Jun 2018 - Dec 2018
Australian Government Contribution:$3,000,000
State:ACT

Project Description

Road failures, collapsing of asphalt road pavement adjacent to concrete sections.

Remove existing asphalt to subgrade level. Treat the subgrade, replace pavement layers, place asphalt. All kerbs are to be re-done and all stormwater sumps are to be adjusted to new level of the road. Existing concrete joints to be treated and new asphalt wearing course to be placed.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 10/05/2018