Outback Way - 2016 Election Commitment - WA - Great Central Road (Ngaanyatjarraku Section) Pavement Upgrades Package 2

Funding Program:Investment Road and Rail Program
Status:In planning
Transport Mode:Road
Expected Start/Finish:Mid 2019 - Late 2021
Estimated Project Cost:$4,160,000
Australian Government Contribution:$3,330,000
State:WA

Project Description

The project involves over nine kilometres of upgrades from gravel to a two-lane seal.

Benefits

The project is expected to deliver the following benefits:

  • reduced travel time for all road users;
  • reduced costs to freight operators and improved route reliability through a decrease in road closures and reduced vehicle operating costs;
  • improved economic opportunities for all industries (such as mining and tourism) through improved access across the region; and
  • reduced accidents by improving the overall safety of the route.

Funding

The Australian Government will provide 80% of the project costs capped up to a contribution of $3.33 million, subject to Western Australia providing 20% of the project costs.

Timetable

Construction is expected to commence in mid-2019, noting that the project is still in the early stages of the development and the above project timeline is subject to change.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 4/05/2018