Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Gawler Rail Line Electrification

Funding Program:National Rail Program
Status:Not started
Transport Mode:Rail
Expected Start/Finish:Mid 2020 - Mid 2026
Estimated Project Cost:$440,000,000
Australian Government Contribution:$220,000,000
Local Council/Shire:Town of Gawler,City of Playford,City of Salisbury
State:SA

Project Description

The Gawler Rail Line Upgrade will continue the electrification of the Gawler rail line in Northern Adelaide from Salisbury to Gawler.

Benefits

Benefits include a faster, safer and more reliable service for the northern Adelaide community to deliver an optimised service plan to cater for patronage uplift and an improved customer experience.

Funding

The Australian Government will provide up to $220 million to this project.

Timetable

The project is expected to commence in mid-2020 and be completed by mid 2026.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 8/05/2018