Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2010 - Dec 2014 |
Australian Government Contribution: | $163,000 |
Local Council/Shire: | Cowra Shire Council |
State: | NSW |
Project DescriptionInadequate width of reinforced concrete box culvert and non existant shoulders coupled with poor pavement shape
Widen 2 cell 2.4 m x 3.0 m Reinforced Concrete Box Culvert including headwalls and guardrail. Augment the roadway on each abutment to suit. Item 8 is the adjoining works
Total cost of proposed project is $178,465 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/03/2015