Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Mar 2012 - Sep 2013 |
Australian Government Contribution: | $329,230 |
Local Council/Shire: | Balranald Shire Council |
State: | NSW |
Project DescriptionFormation of road has deteriorated due to traffic. The road level is below natural surface making it impassable in wet conditions.
To form and build the road up to natural surface with natural material. Then gravel construction 8m wide for a length of 2.0km. this will include grading along the sides of the road to form table drains for drainage flow. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/11/2013