Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Apr 2013 - May 2014 |
Australian Government Contribution: | $263,720 |
Local Council/Shire: | Flinders Council |
State: | TAS |
Project DescriptionDue to increased usage of heavy vehicles and bridge's metal construction failings, the load limit had to be dramatically reduced from 44 tonne to 9 tonne in the recent year. The current timber bridge will require full replacement and the deck span will need a central concrete pillar to be installed to carry the new deck weight.
Full replacement of timber bridge with precast concrete construction with a central pillar.
Total cost of proposed project is $313,576 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014