Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jun 2013 - Jul 2013 |
Australian Government Contribution: | $234,329 |
Local Council/Shire: | Maranoa Regional Council |
State: | QLD |
Project DescriptionThe road has only had one coat bitumen seal applied and now requires a second coat seal to protect the pavement and maintain a smooth road surface
Proposed to apply a second coat bitumen seal to the existing seal |