Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2013 - Apr 2014 |
Australian Government Contribution: | $150,000 |
State: | QLD |
Project DescriptionCurrent road has reached the end of its useful life and requires reconstruction and the intersection is being realigned for safety as there have been several near misses at this location.
Renew any expired drainage. Resheet and seal to a six metre bitumen seal standard (length 4.0km) as well as realign the intersection.
Total cost of proposed project is $300,000 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014