Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jan 2014 - May 2014 |
Australian Government Contribution: | $77,500 |
Local Council/Shire: | Shire of Harvey |
State: | WA |
Project DescriptionPoor road drainage and hazardous roadside edges on causeway and bridge
Side drains to be recontoured to improve out flow. Crash barrier rails to be installed on causeway and bridge over Wokalup Creek
Total cost of proposed project is $232,500 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014