Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2013 - May 2014 |
Australian Government Contribution: | $331,550 |
Local Council/Shire: | Penrith City Council |
State: | NSW |
Project DescriptionThe road was originally constructed in 1979 and is showing signs of deterioration with numerous potholes and extensive failures due to the increasing traffic volume over the years.
It is proposed to mill middle two traffic lanes approximately 7.0 metres wide to a 130mm depth and reconstruct with 100mm asphalt base and provide 30mm asphalt overlay of existing road for a length of 643 metres and width of 12.1 metres |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014