Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Dec 2013 - Jan 2014 |
Australian Government Contribution: | $285,504 |
Local Council/Shire: | Fairfield City Council |
State: | NSW |
Project DescriptionThe road is affected by numerous pavement failures and various types of cracks.Some kerb and gutter sections have been damaged.
The proposed work includes the replacement of road base course with better quality road making material, sealing with spray seal and resurfacing with hot mix asphalt. Length = 460 m, Width = 12.0 m, Area = 5520 m2 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/05/2014